Scm310 ip2 | Operations Management homework help

The template is attached.  Toward the end of the attached powerpoint it explains how to do the template.  I also need a brief analysis of the data.  If you have any questions please let me know.

 

Part 1: Use the provided MRP template to develop a 6-week manufacturing resource plan (MRP), given the following information:

Download the MRP Template

  • The finished product being produced requires 1 of component A, 2 of component B, and 0.5 of component C.
  • The production plan is to have in inventory, ready for sale, 100 units by the end of each of weeks 1–3 and 200 of the finished units by the end of weeks 4–6.
  • All the components A, B, and C must be available at the beginning of the planned production week.
  • Lead times from the vendors for A, B, and C are 1, 2, and 3 weeks respectively
  • Production takes 1 week.

(For example, you would want necessary quantities of A,B, and C in the factory on Monday morning so that the finished units would be available for sale at the end of that same week.)

Part 2: At the bottom of this template, describe the importance of accurate lead time and bill of material information to have an accurate MRP.